News
LCG, October 20, 2025--Holtec International announced today that the Palisades Nuclear Power Plant site in Michigan has received new nuclear fuel – 68 assemblies in total – that achieves a major milestone on the path to restarting the plant. The 800-MW facility was shutdown and decommissioned in 2022 due primarily for economic reasons; however, Holtec is progressing towards restarting the original unit by the end of this year, pending all necessary federal regulatory reviews and approvals. Achieving a successful restart of a shutdown nuclear unit will be a historic first for the nuclear industry.
Read more
|
LCG, October 14, 2025--Calpine Corporation today announced the close of a Texas Energy Fund (TxEF) loan agreement to support development of the Pin Oak Creek project, a 460-MW, natural gas-fired peaking facility adjacent to Calpine's Freestone Energy Center, a gas-fired combined-cycle facility located on approximately 506 acres near Fairfield, Texas.
Read more
|
|
|
Industry News
Perry Nuke Completes Best-ever Refueling in 34 Days
LCG, March 26, 2001--First Energy Nuclear Operating Co. said Friday that operators at its Perry nuclear power plant had returned the facility to service that morning, completing the shortest refueling in the plant's 13-year history.First Energy said the refueling was done in 34 days, shaving three days off the previous best of 37 days set in May 1999. The 1,320 megawatt reactor was operating at 29 percent of capacity this morning, according to the Nuclear Regulatory Commission's daily plant status report. First Energy said output would be gradually increased to 100 percent over the next week or so.During the outage, major work included replacing 304, or about 40 percent, of the plant's 748 fuel assemblies. The new fuel assemblies are equivalent to more than 75,000 train carloads of coal, the company said. One of the turbine rotors also was modified, allowing for increased power output of 5 percent."Our employees met the challenge of safely completing an ambitious work schedule," said JohnWood, site vice president at Perry. "Our team did the right work at the right time to help ensure Perryremains a top performer in the areas of safety and operations."During its last cycle of 655 days, Perry missed only 11 days' work, posting a 98.2 percent capacity factor.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|