|
News
|
LCG, December 18, 2025--RWE and Indiana Michigan Power Company (I&M), an American Electric Power (AEP) company, today announced their partnering to provide new wind power generation capacity online to meet Indiana’s growing electricity demand. The companies signed a 15-year power purchase agreement (PPA) for the total output from RWE’s 200 MW Prairie Creek wind project in Blackford County, Indiana. I&M will purchase electricity from the wind project, which will further diversify its portfolio and be consistent with its all-of-the-above strategy to secure generation for its rapidly growing electricity demand.
Read more
|
|
LCG, December 16, 2025--The Nuclear Regulatory Commission (NRC) announced today that it has renewed the operating licenses of Constellation LLC’s Clinton Unit 1 in Clinton, Illinois, and Dresden Units 2 and 3, near Morris, Illinois, for an additional 20 years beyond the current expiration dates. The combined capacity of these three, Illinois-based nuclear units is 2,925 MW, and the operating license extension will enable the units to generate carbon-free power through about 2050.
Read more
|
|
|
Industry News
CAISO Finds Duke Did Not Withhold Power
LCG, Oct. 28, 2001--An analysis of generators' available capacity during May 8, 2001, a day on which rolling blackouts were ordered in California, has found that while earlier California Public Utilities Commission (CPUC) conclusions concerning generators' withholding of power were substantially correct, Duke Energy did not withhold capacity on that day.The California Independent System Operator (ISO) issued a report Friday in response to a request from state Sen. Joe Dunn (D-Santa Ana), who is investigating last year's energy crisis. The grid operator said that outage data provided by the ISO, which was used as the basis for a report last month by the CPUC, may have led the commission to make conclusions about specific generators' reasons for outages which may or may not be correct. The ISO stated in its report that Unit 3 of Duke's Morrow Bay plant was on scheduled outage on May 8, 2001, and that the ISO had asked some of Duke's other generators to reduce output, meaning no remaining capacity was available from the company.According to the ISO, generators did have power available that was not bid into the market and were not always responsive to the grid operators' emergency orders. These behaviors did contribute to a difficult situation when the ISO required power in particular areas, according to its report. The ISO said however, that in discussing the usage of its outage data with the CPUC that the commission "may have used outage data that was useful for depicting outages on a macro level but which was not appropriate for investigation of unit-specific behavior during a specific subset of hours."Among the considerations that the ISO said were not explicitly accounted for in the earlier CPUC report were generating units' ability to increase output at a certain rate, the units' actual capacity as opposed to their rated capacities, and the need to have units back down their output to provide more power later if necessary. Transmission constraints and ISO's need to maintain stable conditions on the grid were also cited by the ISO as not appearing in the CPUC findings.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|